Cat Linh-Ha Dong railway nears completion

(VOVworld) - The Cat Linh-Ha Dong elevated railway is scheduled to be put into trial operation in October and officially launched on December 31, General Director of Railway Project Management Unit Le Kim Thanh said. 

Cat Linh-Ha Dong railway nears completion - ảnh 1


He said that 70 percent of the railway project had been completed since it broke ground in September 2010. Thirty percent of the project was finished in 2015 alone. The management board of the project was making efforts to finish installing girders by the middle of April while stations and a depot were set to be completed in June to install facilities by the end of September.